Project Timeline
A visual overview of project milestones.
Shore Pile Driving
Dec 18 - Apr 24, 2022
Initial Earth Excavation
May 14 - May 19, 2022
Tie Beam Casting Work
May 22 - Jun 22, 2022
Brick work, Sand filling & Soling
Jun 4 - Jun 29, 2022
Railing Around The Tie beam
Jun 25 - Jun 30, 2022
Earth Excavation (1st Layer)
Aug 1 - Aug 7, 2022
Bracing work (1st Layer)
Aug 7 - Aug 21, 2022
Tarpulin Covering
Aug 16 - Sep 25, 2022
Earth Excavation (2nd Layer)
Aug 22 - Sep 10, 2022
Bracing work (2nd Layer)
Sep 3 - Sep 28, 2022
Earth Excavation (3rd Layer)
Sep 20 - Oct 23, 2022
Leveling, Dressing and C.C Work
Nov 1 - Nov 6, 2022
Ferro cement plaster works
Nov 2 - Nov 22, 2022
Mat Re-bar binding works
Nov 23 - Dec 1, 2022
Mat Casting works
Dec 2 - Dec 2, 2022
B-3 Roof slab casting work
Dec 4 - Jan 25, 2023
B-2 Roof slab casting works
Feb 5 - Apr 13, 2023
B-1 Roof slab casting works
May 5 - Jun 21, 2023
Ground floor roof slab casting
Jul 10 - Sep 3, 2023
1st Floor roof slab casting
Sep 4 - Oct 4, 2023
2nd Floor roof slab casting
Oct 7 - Nov 5, 2023
3rd Floor roof slab casting
Nov 6 - Dec 6, 2023
4th Floor roof slab casting
Dec 7 - Jan 4, 2024
5th Floor roof slab casting
Jan 5 - Feb 3, 2024
6th Floor roof slab casting
Feb 4 - Mar 5, 2024
Electromechanical room
Mar 15 - Apr 1, 2024
All Brick work & Plaster work
Feb 25 - Apr 30, 2024